Bay St. Louis boardwalk construction is set to resume Nov. 7

The Daily Biloxi teamFrom today’s edition · 1 min read · 2 sources

ShareEmailFacebookX

If you've walked the along downtown Bay St. Louis, work is set to resume Nov. 7 on the boardwalk being built on top of it. It will extend the ADA-accessible walkway more than 500 feet, from Demontluzin Avenue to Ulman Avenue. Principal engineer Jason Chiniche says the second half of phase two should take about six months.

Two funding sources are paying for the boardwalk

Source: wlox.com

View as table
Value
Outdoor Stewardship Trust Fund$0.5 million
Gulf Coast Restoration Funds$1.3 million

WXXV reports the finished boardwalk will have benches and picnic tables, plus multiple ADA ramps to the beach. All four phases should be done by fall 2027.

  • Done: phase one and part of phase two
  • Phase three: small pier with ADA access to the beach fire pit
  • Phase four: would connect the beach and harbor

The boardwalk has taken a decade to reach its last phases

  1. 2016Talks on making the ADA-accessible begin under Mayor Les Fillingame.
  2. Nov. 7Work will resume on the second half of phase two.
  3. Fall 2027All four phases should be complete.

Sources: WXXV News 25, wlox.com